North Shore Study Area

Print
Press Enter to show all options, press Tab go to next option
   WHAT ARE WE DOING

 

  • October 3, 2018: Per the Crystal Lake Park District, the berm extension project along the south end of the Lippold Park, north of Crystal Beach and Lakewood Avenues is out for bid. They anticipate awarding the contract the end of October with construction commencing shortly after. 
  • September 26, 2018:  The surveyors are onsite the week of September 24, 2018. 
  • September 5, 2018: City staff held a kickoff meeting with the design consultant for the new storm sewer. Design is now underway. 
  • August 29, 2018: Staff submitted a concept paper for the 2019 McHenry County Community Development Block Grant funding program to fund a portion of the construction. A kickoff meeting with the design consultant for the design of the new storm sewer is scheduled for September 5. 
  • August 7, 2018: Christopher B. Burke Engineering was selected to complete the design engineering and permitting for the installation of the new storm sewer in the right-of-way and BMP basins.
  • July 19, 2018:   The City of Crystal Lake will be conducting additional tree and brush removal in the area behind the homes on the east stretch of North Shore Drive starting on July 26. The City's work will consist of removing trees more than 10 feet away from the power lines on City property. ComEd has completed some initial trimming in that area, and will be scheduling more trimming. 
  • June 19, 2018: ComEd crews have begun tree trimming in the North Shore neighborhood. This trimming will include the area behind the homes on the east stretch of North Shore. Once they have completed their trimming work on the east section of North Shore Drive, ComEd will take out trees that are immediately adjacent to their lines on City property.  Once ComEd is done, we will perform additional clearing on the City owned property to create a buffer from the ComEd lines to reduce the potential for storm related outages from trees.

Additionally, the City continues its aggressive maintenance of the Cove Pond grates and East Street swale. The City recently hired a contractor to treat the west end of Cove Pond with a water-safe herbicide (similar to how the Park District treats the Lake) to cut down on the waterfoil invasive weeds. This should reduce the volume of weeds that drift into the grate.

  • Spring/Summer 2018: The Crystal Lake Park District is in the design and permitting stage for the modifications to the existing berm along the south end of Lippold Park.  
  • February 1, 2018: City staff met with the residents of the North Shore for a final check-in. View the presentation slides.
  • January 22, 2018: Letters were mailed to all the residents in the North Shore Area inviting them to the open house. 
  • September 21, 2017: City staff met with residents of the North Shore. Meeting minutes are available here. View the presentation slides. 
  • September 6, 2017: City staff met with the Lake Street Beach Association as a follow-up to the previous meeting. View the presentation slides. Meeting minutes available here
  • August 11, 2017: City staff met with the Crandall/Baldwin residents. Meeting minutes are here
  • August 4, 2017: Letters were mailed to all residents in the North Shore area notifying them of the open house on September 21, 2017. 
  • August 2, 2017: City staff met with the Lake Street Beach Association. Meeting minutes are here
  • August 2, 2017: Walking tour with the NCLPBIA board. Meeting minutes are here
  • July 24, 2017: City staff met with the NCLPBIA board members. Meeting minutes are here.
  • July 18, 2017: City Council presentation to review the stakeholder engagement process to review and refine improvements to reduce the risk of flooding.
  • June/July 2017: City experienced successive and extreme rain events leading to the total rainfall for June and July of almost 20 inches, over double the normal average.
  • May 2017: City staff reached out to the North Crystal Lake Park Beach Improvement Association (NCLPBIA) to re-initiate discussions regarding area flooding north of the Lake.
  • November 19, 2012: Construction of the North Shore Drive project substantially complete.
  • For complete history, click here
   HISTORY
North Shore Study Area 
  • Many of the homes were initially built in the 1920s and 1930s as summer cottages and three-season homes.
  • After World War II, many of these homes were converted to year-round residences.
  • In the late 1960s, the residents of North Crystal Lake Park Beach annexed into Crystal Lake and water main and sanitary sewer services were extended throughout this area.
  • In the late 1990s, the residents of NCLPBIA annexed into Crystal Lake and water main and sanitary sewer services were extended throughout the subdivision.  At that time, the residents declined the installation of stormwater facilities, due to the cost.
  • Flooding in this area occurs in the FEMA floodplain.

  • Flooding also occurs due to pocketed areas (low spots with no outlet) which may or may not receive stormwater from adjacent roadways and the duration of the flooding (length of standing water) varies by location.

   COMMENTS
We want to hear from you! Please submit your questions, concerns, and stories to: stormwatersolutions@crystallake.org

Please don't forget to include your name, address, and phone number so the City can get back to you. Pictures are appreciated, but the City can't receive emails with a total of over 10 MB of attachments.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer