Street Resurfacing Program

Print
Press Enter to show all options, press Tab go to next option

Resurfacing

Project Background:

  • Surface condition of all City maintained streets is evaluated annually.
  • Streets for the annual program are selected based upon this evaluation.

Project Contact:

Jason MacNally, Engineering and Building Inspector
Cell Phone: (815) 790-6948
Email: jmacnally@crystallake.org

2018 Street Resurfacing Program Updates: 

  • September 19, 2018:  The paving in the Crystal Ridge area is complete. Pavement striping and restoration work remain.   
  • September 12, 2018: The Wastewater Treatment Plant parking lot is complete. Pavement removals and placement of the first layer of asphalt in the Crystal Ridge area is complete. The contractor will start placing the final surface layer of asphalt in the Crystal Ridge area on September 13.  
  • September 5, 2018:  The contractor continued working on the Wastewater Treatment Plant parking lot and anticipates placing the final layer of asphalt next week. The contractor started pavement removals in the Crystal Ridge area. Placement of the first level of asphalt will commence over the next week.   
  • August 29, 2018: The contractor started working on the Wastewater Treatment Plant parking lot. Pavement removal along Crystal Ridge will start on August 30. The contractor will leave the roadway in a safe, passable condition for the long holiday weekend.   
  • August 22, 2018: The contractor completed the Beardsley Parking Lot west and the adjacent alley as well as Park, View, and Rebecca Streets. The contractor will start the Crystal Ridge area around September 4.  
  • August 15, 2018:  The contractor will complete the Beardsley Parking Lot west and the adjacent alley on August 16 with parking lot striping occurring on August 20, weather permitting. The final surface layer of asphalt will be complete on Park, View, and Rebecca Streets on August 17, weather permitting. The contractor will start the Crystal Ridge area around September 4.  
  • August 8, 2018: The contractor anticipates returning on August 10 on Park, View and Rebecca Streets. After those streets are complete, they will complete the Beardsley Parking Lot west and the adjacent alley.  The City inspector will talk to each of the affected businesses about the alley work and the patrons of the businesses will be able to park in the Beardsley Parking Lot east lot (that was previously completed).   
  • August 1, 2018: The contractor anticipates being back in town the week of August 13; however, this is contingent upon work production and completion of some other projects the contractor is working on completing.
  • July 18, 2018:  Paving work is complete on the Beardsley Street East parking lot. The contractor will be working in another municipality for the next 3 to 4 weeks and will return to the City to finish the streets in the northern area of town at that time. All areas around the school have been completed.
  • July  11, 2018: Paving work is complete in the Hunters Ridge/Woodscreek area. Pavement removal and base preparation will commence at Wastewater Treatment Plant 2 and the Beardsley Parking Lot next.
  • June 21, 2018: The paving contractor will be starting pavement removal on June 21 in the Hunters Ridge/Woodscreek area, pending weather.
  • June 13, 2018: The paving contractor started saw cutting and pavement removal is anticipated to start next week in the Hunters Ridge/Woodscreek area.
  • June 6, 2018: The paving contractor anticipates starting saw cutting and pavement removal in the next few weeks on the south end of the City (Hunters Ridge/Woodscreek area). The exact start date is not known at this time.   
  • May 10, 2018: The concrete contractor completed the concrete work for the resurfacing program and is currently working on restoration.  
  • May 3, 2018: The concrete contractor continues working on curb removal and replacement as well as the sidewalk ramp improvements to meet ADA requirements.  
  • March 20, 2018: City Council awarded the contract for the 2018 Street Resurfacing Program to Geske and Sons.  
  • March 2, 2018: Bids were opened for the 2018 Street Resurfacing Program. Geske and Sons was the low bidder.

Project Scope:

Streets Included in 2018 Street Resurfacing Program

Street

From

To

Short Street

Ellsworth Avenue

West End

Main Street Alley

Beardsley Street

South End

Crystal Ridge Dr

Carmella Drive

Walkup Road

Revere Drive

Talismon Drive

Crystal Ridge Drive

Carmella Drive

Revere Drive

Crystal Ridge Drive

Mira Street

Talismon Drive

Carmella Drive

Talismon Drive

Talismon Court

Walkup Road

Talismon Court

Talismon Drive

Mira Street

Parkview Court

Walkup Road

Carmella Drive

Diamondo Street

Talismon Drive

Talismon Court

Rebecca Street

Main Street

McCullum Street

View Street

Lorraine Drive

East End

Hedrick Street

View Street

North End

Park Boulevard

View Street

Route 176

Hunters Trail

Swanson Road

Dogwood Drive

Harper Lane

Hunters Trail

Williamsburg Lane

Flagstone Drive

Hunters Trail

Hunters Trail

Williamsburg Lane

Swanson Road

Moorland Lane

Moorland Lane

Village Road

North End

Crandon Place

Hunters Trail

North End

Crandon Court East

Crandon Place

East End

Crandon Court West

Crandon Place

West End

Dogwood Drive

Alexandra Blvd

Driftwood Lane

Lilac Drive

Alexandra Blvd

Driftwood Lane

Wastewater Treatment Plant 2

NA

NA

Beardsley Commuter Parking Lots

NA

NA

Ellsworth Street

181 Ellsworth

185 Ellsworth

Pingree Road

UPRR

Approx. 75 ft North

Glen Avenue Alley

IL Rte. 176

Glen Avenue